PASSYUNK AVENUE DRAWBRIDGE
CAMPBELL, OH
PROJECT INFORMATION
Project Number ECMS #62694
Passyunk Avenue Drawbridge Rehab Installation of Shielding and Containment
Competent Person: Philip Dawson
Personnel Employed: 6
2/16 – CURRENT
PROJECT DETAILS
Materials Applied:
Orgaince Zinc, Epoxy, and Polyurethane
Equipment Used:
Air compressors, needle guns, decon facility, grinders,brushes, rollers, traffic control devices, etc.
Environmental Controls:
Class 1A, 3P Containment
Ventilation Methods:
Dust collection
Coating Removal Methods:
Sand Blasting, Needle Guns, and Grinders.
Special Requirements:
Rapid Deployment, containment, collection and disposal of waste Bascule Span shielding